System and Infrastructure Status News
Delta and DeltaAI work file system unavailable
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: delta-cpu.ncsa.access-ci.org, delta-gpu.ncsa.access-ci.org
Start Date: December 11, 2025, 7:00 p.m.
End Date: December 12, 2025, 7:30 a.m.
The hardware and software issues encountered during the upgrade of the /work file system have been resolved. The file system is now available and the job scheduler was resumed. All but one root cause analysis has been completed, and we will work with vendor engineering on the remaining root cause. We apologize of the inconvenience caused by this unplanned outage. -Delta and DeltaAI projects. The Delta and DeltaAI /work file system is currently unavailable due to an unforeseen hardware failure during a software update. NCSA continues to work with the vendor to replace the hardware and complete the software update. New jobs are being blocked from starting, which includes jobs submitted via Delta and DeltaAI Open OnDemand portals. Additional updates will be sent when a return to service is known. We apologize for the inconvenience. -Delta and DeltaAI projects.
Posted: March 20, 2026
Complete - Anvil Maintenance on December 11, 2025
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: anvil.purdue.access-ci.org, anvil-gpu.purdue.access-ci.org
Start Date: December 11, 2025, 12:00 p.m.
End Date: December 11, 2025, 10:51 p.m.
UPDATE: December 11, 2025 05:51 PM ET As of 5:51pm ET, the maintenance work on Anvil has been completed and job scheduling has been resumed. If you encounter any issues post maintenance, please contact ACCESS Help Desk (https://support.access-ci.org/help-ticket). Original Post: The Anvil system will be unavailable on December 11th, 2025, from 7:00 AM to 6:00 PM ET for scheduled maintenance. During this maintenance, we will perform NVIDIA driver upgrades and rebuild Slurm with PMIx. Any Slurm jobs requesting a walltime that would extend past Thursday, December 11th at 7:00 AM ET will not start and will remain in the queue until after maintenance is completed. If you have any questions, please submit a ticket through the ACCESS Help Desk (https://support.access-ci.org/help-ticket).
Posted: March 20, 2026
Dec 2: Jetstream2 networking updates
PublishedInfrastructure News Type: Reconfiguration
Affected Infrastructure: jetstream2.indiana.access-ci.org
Start Date: December 2, 2025, 12:00 p.m.
End Date: December 3, 2025, 2:00 a.m.
On December 2, Jetstream2 engineers will be performing updates to Jetstream2's networking infrastructure to enable DNS resolution over IPv6. There is no expected downtime or impact to users for this maintenance. If you have any questions, please contact Jetstream2 Support by emailing help@jetstream-cloud.org
Posted: March 20, 2026
TAMU ACES storage recovered from an outage
PublishedInfrastructure News Type: Degraded
Affected Infrastructure: aces.tamu.access-ci.org
Start Date: November 18, 2025, 7:40 p.m.
End Date: November 18, 2025, 9:55 p.m.
TAMU ACES had a storage outage at 1:40 pm ~ 3:55 pm CST, Nov 18, 2025. ACES storage is now back to normal.
Posted: March 20, 2026
ACCESS Duo Phone Call Authentication
PublishedInfrastructure News Type: Outage Partial
Affected Infrastructure: identity.access-ci.org
Start Date: November 14, 2025, 2:00 p.m.
End Date: Not Specified
Dear ACCESS Community, The telephony credits available in the ACCESS DUO account unexpectedly ran out the evening of November 13, 2025. Those employing phone-call-based authentication for DUO have been getting denied by DUO as a result. We are working as quickly as possible to purchase additional credits to resolve this issue, but due to university purchasing policies there may be a delay before the credits become available. We regret the inconvenience of this sudden suspension of phone-call-based DUO authentication and direct all affected members of the community to select one of the several alternative methods of DUO authentication described at https://guide.duo.com/ (https://6fax6u7ab.cc.rs6.net/tn.jsp?f=0013UWUxb0WeMD2uTMupnTB5qASFg_xjuvzRv6psbGE-sHyF1oKWQHpPQPMXpJQTcmCsz4DD0QMrM_Zr_-CuaS16vi7zC0LbABPDsWRaN5qEDYmxKVBPwE-rPE1kySrVmUydiFBxNXlBNEAXRlH6OjmcA==&c=10ka7qroOSdY1qz0BlkWJMDU9CFOeZlw2SrKzSFTMJhvlleLJztGtg==&ch=U2-7NbP4COXJ3gs0XcWUE4Sc_viAYFAi2FOggUXfAc3nNQT82t1-RQ==). More than 90% of ACCESS community members already employ Duo Push (https://guide.duo.com/universal-prompt#duo-push) or a Platform Authenticator (e.g., passkey), and we strongly recommend that those currently configured for phone-call-based DUO authentication switch to one of these better methods. If you need assistance to update your DUO authentication method, please open a ticket at https://support.access-ci.org/help-ticket and select "I need help logging into ACCESS website" as the ticket type. We anticipate a surge in help desk tickets to help those affected, and we appreciate your patience as we work to help you as soon as we can. Regards, ACCESS Cybersecurity Team
Posted: March 20, 2026
Updated idp.access-ci.org
PublishedInfrastructure News Type: Reconfiguration
Affected Infrastructure: identity.access-ci.org
Start Date: November 10, 2025, 2:30 p.m.
End Date: November 10, 2025, 2:40 p.m.
On November 10, 2025, the ACCESS Identity Provider (https://idp.access-ci.org/idp) (idp.access-ci.org) was updated to Tomcat v10.1.48 to address a security issue (https://nvd.nist.gov/vuln/detail/CVE-2025-61795).
Posted: March 20, 2026
TAMU Launch Maintenance
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: launch.tamu.access-ci.org
Start Date: October 25, 2025, 2:00 p.m.
End Date: October 27, 2025, 4:00 a.m.
Updated: 10:25 pm CDT, Oct 26, 2025. Launch cluster maintenance has completed. All queued jobs are running. The TAMU Launch cluster will be unavailable from 9a CDT Saturday October 25 to 11pm CDT Sun October 26 for regular and storage maintenance.
Posted: March 20, 2026
Operations Portal Upgrade Outages, 2025/10/24
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: dashboard.operations.access-ci.org
Start Date: October 24, 2025, 7:00 p.m.
End Date: October 24, 2025, 8:00 p.m.
The ACCESS Operations Dashboard was down for about an hour to apply fixes and upgrades. The following application(s) were affected: - Resource Provider Integration Dashboard (https://dashboard.operations.access-ci.org/dashboard/integration/) The following new applications were released during the upgrade: - ACCESS Staff Dashboard PREVIEW (https://dashboard.operations.access-ci.org/dashboard/integration/concierge/dashboard) - ACCESS Resource Integration Summary View (https://dashboard.operations.access-ci.org/dashview/resource_summary)
Posted: March 20, 2026
Unplanned service interruption on DeltaAI and reduced service on Delta
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: delta.ncsa.access-ci.org
Start Date: October 23, 2025, 2:04 p.m.
End Date: October 23, 2025, 6:00 p.m.
A facility event has caused a full outage on DeltaAI and a partial outage on Delta. We will return the affected nodes to service as soon as we can. -The Delta and DeltaAI projects
Posted: March 20, 2026
ACCESS XDMoD Planned Downtime
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: xdmod.access-ci.org
Start Date: October 16, 2025, 2:00 p.m.
End Date: October 17, 2025, 2:00 p.m.
The ACCESS XDMoD portal will temporarily be unavailable on 10/16/2025, from approximately 09:00 EST until the following day, 10/17/2025, 09:00 EST. The service will be completely unavailable for routine infrastructure updates. An update will be posted once the update is complete. We apologize for any inconvenience this might cause. UPDATE: The update has completed successfully and the service is available again.
Posted: March 20, 2026
Upcoming Jetstream2 GPU maintenance on October 7, 2025
PublishedInfrastructure News Type: Outage Partial
Affected Infrastructure: jetstream2-gpu.indiana.access-ci.org
Start Date: October 7, 2025, 12:00 p.m.
End Date: October 8, 2025, 12:00 a.m.
Jetstream2 GPU resources will undergo routine monthly maintenance on October 7, 2025 from approximately 11AM to 11PM UTC (convert to local time (https://dateful.com/convert/utc?t=11am)). This maintenance will include firmware updates and other necessary changes to improve GPU performance. During this maintenance window users may experience intermittent delays and unavailability of their GPU resources. As always, we will do our best to keep disruptions to a minimum during this time. We strongly advise preserving your work prior to October 7 by: - Safely shutting down any active processes or jobs - Backing up essential data outside of Jetstream2 Please note: Jetstream2 CPU, Large Memory, and Storage resources will not be affected. If you have any questions or concerns, please contact Jetstream2 Support at help@jetstream-cloud.org.
Posted: March 20, 2026
TAMU Launch Maintenance
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: launch.tamu.access-ci.org
Start Date: September 27, 2025, 11:00 p.m.
End Date: September 30, 2025, 5:00 p.m.
The Launch cluster maintenance has been extended to 12pm CDT Tuesday September 30 The TAMU Launch cluster will be unavailable from 6p CDT Saturday September 27 to 10a CDT Monday September 29 for regular maintenance and the 9/28 data center partial power outage. Quotas will also be enabled for user/project scratch directories during this maintenance window
Posted: March 20, 2026
TAMU ACES Partial Downtime
PublishedInfrastructure News Type: Outage Partial
Affected Infrastructure: aces.tamu.access-ci.org
Start Date: September 27, 2025, 11:00 p.m.
End Date: September 29, 2025, 3:00 p.m.
The TAMU ACES cluster will be operating at reduced capacities with a subset of nodes powered down during data center power maintenance from 6p CDT Saturday September 27 to 10a CDT Monday September 29.
Posted: March 20, 2026
Complete - TACC Status Saturday September 27, 2025
PublishedInfrastructure News Type: Degraded
Affected Infrastructure: stampede3.tacc.access-ci.org, ranch.tacc.access-ci.org
Start Date: September 27, 2025, 5:06 a.m.
End Date: October 1, 2025, 5:00 p.m.
Final Update: 10/1/2025 14:15 CDT All ACCESS available TACC resources are now back in full production. If you have questions about other TACC resources you can refer to User Updates here: https://tacc.utexas.edu/news/user-updates/ ---- Update: 09/30/2025 17:00 CDT Most TACC services have been restored since Saturday’s power outage. Thanks to the dedicated work of the team, all large systems are in production, with the exception of Frontera which is running a limited number of jobs while performance issues on one of the scratch filesystems are addressed. You may see some services at less than 100% throughput while replacement parts trickle in for components that were damaged. If anything appears offline that should not be, please submit a ticket here: https://tacc.utexas.edu/portal/tickets Thank you for your continued patience while the admins continue to work to restore services. ---- UPDATE: 9/29/25 Stampede3 has partially recovered from an emergency maintenance. /corral is not available and queues will be operating with reduced node counts as we work to bring the system back up to 100%. ---- Original - 9/27/25 The Texas Advanced Computing Center facilities experienced a site wide power outage at 6:12 am CDT. At this time, admins are on site and working to restore all systems to production.
Posted: March 20, 2026
Anvil Cluster Open Ondemand Maintenance - Sep 23
PublishedInfrastructure News Type: Reconfiguration
Affected Infrastructure: anvil.purdue.access-ci.org, anvil-gpu.purdue.access-ci.org
Start Date: September 23, 2025, 1:00 p.m.
End Date: September 23, 2025, 9:00 p.m.
Update: As of 10:30 am EDT, September 23, 2025, we have finished Anvil Open OnDemand Dashboard upgrade. We are thrilled to announce the launch of the new version of our re-designed dashboard for Open OnDemand on Anvil! This upgrade is designed with a more intuitive interface and a host of more powerful new features to enhance your experience on Anvil. Please check the original post for the overview of all the amazing new features AND Get Started Today Access the new dashboard by visiting https://ondemand.anvil.rcac.purdue.edu. We’ve prepared a comprehensive guide (see “New Features” page in the new dashboard) to help you navigate and make the most out of the new features. Have questions? Need assistance? Require more features? Our support team is here to help! Contact us through ACCESS Help Desk at https://support.access-ci.org/help-ticket (https://support.access-ci.org/help-ticket**). We’d love to hear your feedback as you explore the new gateway. Your input is invaluable in shaping the future of our HPC services. Thank you for being part of this journey. Let’s push the boundaries of discovery together! Original post: The Open Ondemand service for Anvil will be unavailable from Tuesday, September 23 at 9:00am EDT, 2025 to Tuesday, September 23 at 5:00pm EDT, 2025. During the maintenance, Anvil team will perform a reconfiguration to the Open Ondemand dashboard for Anvil which will upgrade the current dashboard to a new version with new features listed below. What’s New on the dashboard v2? - New UI design: Brand new UI design to present a more modern look. - Anvil AI Partition Status: Adding partition status check for the new Anvil AI partition. - Cluster Status and Node Status: Allow users to have a glance of overall Anvil cluster status or dive deep into the status for specific compute node. - New Announcement Widget: Now you can view past announcements with a scroll! - New My Jobs page: Adding more features to My Jobs page. - New Job page: View or control your specific jobs more easily through the job page. - New Performance Metrics page: Now you can view your job performance metrics on Anvil within any time span. What will impact you? - All Slurm jobs on Anvil (including jobs that have already submitted through Open Ondemand before this maintenance) will continue and NOT be impacted. - All functions related to Open Ondemand including login will be unavailable during the maintenance. Anvil Open Ondemand service will return to full production by Tuesday, September 23 at 5:00pm EDT, 2025. Please submit a ticket through ACCESS Help Desk at https://support.access-ci.org/help-ticket (https://support.access-ci.org/help-ticket**) if you have any questions or suggestions.
Posted: March 20, 2026
SDSC Expanse Maintenance: 6AM-2PM (PT), September 22, 2025 [completed]
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: expanse.sdsc.access-ci.org, expanse-gpu.sdsc.access-ci.org
Start Date: September 22, 2025, 1:00 p.m.
End Date: September 22, 2025, 9:00 p.m.
Dear Expanse User, The Expanse Slurm maintenance has been completed and we have released the reservation. The system is running submitted jobs per available resources and priority. Thanks SDSC User Services >>>> Dear Expanse User, The maintenance on Expanse is taking longer than expected and we are extending the maintenance reservation to 6PM(PT). We will update once the maintenance is complete. Thanks SDSC User Services Staff >>>>> Dear Expanse User, We will have a maintenance on Expanse 6AM-Noon (PT), September 22, 2025. During this maintenance we will reconfigure the Slurm scheduler to remove some nodes that were moved to a different cluster. We have a reservation in place to prevent jobs from running during this maintenance. The "squeue" output will show "ReqNodeNotAvail, Reserved for maintenance" for jobs that do not fit in the time period before the maintenance begins. These jobs will run after we release the maintenance reservation. Thanks SDSC User Services Staff
Posted: March 20, 2026
TAMU ACES and Launch Partial Downtime
PublishedInfrastructure News Type: Outage Partial
Affected Infrastructure: aces.tamu.access-ci.org, launch.tamu.access-ci.org
Start Date: September 19, 2025, 11:00 p.m.
End Date: September 21, 2025, 5:00 a.m.
The TAMU ACES and Launch clusters will be be operating at reduced capacities with a subset of nodes powered down during data center power maintenance from 6p Friday September 19 to midnight Sunday September 21.
Posted: March 20, 2026
PSC Bridges-2 Maintenance
PublishedInfrastructure News Type: Outage Full
Affected Infrastructure: bridges2-em.psc.access-ci.org, bridges2-gpu.psc.access-ci.org, bridges2-rm.psc.access-ci.org, bridges2-ocean.psc.access-ci.org
Start Date: September 19, 2025, 6:00 p.m.
End Date: September 19, 2025, 9:00 p.m.
PSC Bridges-2 is currently unavialable. Our admins are working to restore the system to full service.
Posted: March 20, 2026
Update registry.access-ci.org Plugins
PublishedInfrastructure News Type: Outage Partial
Affected Infrastructure: registry.access-ci.org
Start Date: September 8, 2025, 2:00 p.m.
End Date: September 8, 2025, 2:30 p.m.
On September 8, 2025, several plugins used by the ACCESS User Registry (https://registry.access-ci.org/) will be updated. The following features will be improved: - Update the DynamoDB provisioner to include group numbers along with group names - Update text on the Select Your Organization page during user enrollment - Set/unset a session cookie used by the ACCESS universal navigation bar so login/logout links work - Store users' PHP sessions in DynamoDB to deter creation of multiple user enrollment petitions Server instances will be restarted during this update which may cause in-progress registrations/logins to fail. If you experience issues during the update, please open a ticket (https://support.access-ci.org/help-ticket).
Posted: March 20, 2026
idp.access-ci.org Updated
PublishedInfrastructure News Type: Reconfiguration
Affected Infrastructure: identity.access-ci.org
Start Date: August 28, 2025, 2:00 p.m.
End Date: August 28, 2025, 2:30 p.m.
On August 28, 2025, the ACCESS Identity Provider (https://idp.access-ci.org/idp) (idp.access-ci.org) was updated to v5.1.6 to address a security issue (https://shibboleth.net/community/advisories/secadv_20250826.txt).
Posted: March 20, 2026